210 - Create/update project and activity
From Host
| Field | Description | Data Type | Mandatory | Comment |
|---|---|---|---|---|
| 1 | Project id | Text(25) | X | |
| 2 | Project description | Text(80) | X | |
| 3 | Ref 1 | Text(40) | ||
| 4 | Ref 2 | Text(40) | ||
| 5 | Ref 3 | Text(40) | ||
| 6 | Planned project start date | Date | Dates must be entered correctly e.g. start date should be less or equal to end date | |
| 7 | Planned project end date | Date | Dates must be entered correctly e.g. start date should be less or equal to end date | |
| 8 | Only one activity | Logical | ||
| 9 | Activity id | Text(25) | ||
| 10 | Activity description | Text(80) | ||
| 11 | Planned activity start date | Date | ||
| 12 | Planned activity end date | Date | ||
| 13 | Planned activity time | Time duration | ||
| 14 | Legal employees | Text | There can be several employees/departments separated with a comma. In this case the general field separator must not be a comma. The employee(s) and department(s) must exist in ProMark. | |
| 15 | Legal departments | Text | There can be several employees/departments separated with a comma. In this case the general field separator must not be a comma. The employee(s) and department(s) must exist in ProMark. | |
| 16 | Activity status | Text | This field directly corresponds to the ''Status'' field in the set-up screen for activities in ProMark. | |
| 17 | Account | Text | To remove an existing account assignment, the host can place an underscore in the field, otherwise, if the field has no content, any existing account assignment is preserved. | |
| 18 | Project status | Text | This field directly corresponds to the ''Status'' field in the set-up screen for projects in ProMark. | |
| 19 | Setup id | Text | This field directly corresponds to the ''Project profile'' field in the set-up screen for activities in ProMark. | |
| 20 | Division id | Text | ||
| 21 | Project template | Text | This field is a project id used for template. The project create will copy all activities from this template project to the project created. | |
| 22 | Created/updated by | Text(6) | ||
| 23 | Activity approval group | Text | ||
| 24 | Block registrations | Logical | Block for registrations | |
| 25 | Auto distribution | Logical | Auto distribute time according to budget (see 215) | |
| 26 | No maint. of activity/piecework on the portal | Logical | This field is only used if Piecework is activated on projects. When field is set to ''True'' then it's not possible to maintain Activity/Piecework on the project from the Portal. | |
| 27 | Fixed project dimension 1 | Text | ||
| 28 | Fixed project dimension 2 | Text | ||
| 29 | Fixed project dimension 3 | Text | ||
| 30 | Fixed project dimension 4 | Text | ||
| 31 | Fixed project dimension 5 | Text | ||
| 32 | Fixed activity dimension 1 | Text | ||
| 33 | Fixed activity dimension 2 | Text | ||
| 34 | Fixed activity dimension 3 | Text | ||
| 35 | Fixed activity dimension 4 | Text | ||
| 36 | Fixed activity dimension 5 | Text | ||
| 37 | 2nd level appr. group on project | Text | Identification of secondary approval group for the project. This field will only be used if there is a secondary approver on the approval group, and then it will replace that. | |
| 38 | Create missing approval group | Logical | Y = If the approval group in the tranaction doesn't exist it will be created | |
| 39 | Approval group | Text | List of approval groups separated by comma. If the group doesn't exist, it is created. Description will be the same as the id. | |
| 40 | Approval user | Text | Comma separated list of users that can approve this approval group | |
| 41 | Replace approvers | Logical | Y = All existing approvers on this group will be deleted before the new approvers are added | |
| 42 | Approval level | Integer | 0 - Can not approve at all | |
| 43 | Project dimension 1 is locked | Logical | Default value is TRUE. If this is set to FALSE, value on 'fixed project dimension 1' is set as default value otherwise it is locked. | |
| 44 | Project dimension 2 is locked | Logical | Default value is TRUE. If this is set to FALSE, value on 'fixed project dimension 2' is set as default value otherwise it is locked. | |
| 45 | Project dimension 3 is locked | Logical | Default value is TRUE. If this is set to FALSE, value on 'fixed project dimension 3' is set as default value otherwise it is locked. | |
| 46 | Project dimension 4 is locked | Logical | Default value is TRUE. If this is set to FALSE, value on 'fixed project dimension 4' is set as default value otherwise it is locked. | |
| 47 | Project dimension 5 is locked | Logical | Default value is TRUE. If this is set to FALSE, value on 'fixed project dimension 5' is set as default value otherwise it is locked. | |
| 48 | Activity dimension 1 is locked | Logical | Default value is TRUE. If this is set to FALSE, value on 'Fixed activity dimension 1' is set as default value otherwise it is locked. | |
| 49 | Activity dimension 2 is locked | Logical | Default value is TRUE. If this is set to FALSE, value on 'Fixed activity dimension 2' is set as default value otherwise it is locked. | |
| 50 | Activity dimension 3 is locked | Logical | Default value is TRUE. If this is set to FALSE, value on 'Fixed activity dimension 3' is set as default value otherwise it is locked. | |
| 51 | Activity dimension 4 is locked | Logical | Default value is TRUE. If this is set to FALSE, value on 'Fixed activity dimension 4' is set as default value otherwise it is locked. | |
| 52 | Activity dimension 5 is locked | Logical | Default value is TRUE. If this is set to FALSE, value on 'Fixed activity dimension 5' is set as default value otherwise it is locked. |